Construction progress

Ready
Work is in progress
Planned construction
APARTMENT DELIVERY DATE
Transfer of apartments - Q3 2023
Transfer of apartments - Q3 2023
100%
Construction of reinforced concrete monolithic structures above 0
100%
Installation of a parking roof
100%
Construction of external and internal walls, partitions
100%
Construction of the main roof
100%
Installation of facades, stained glass, windows, doors
100%
Installation of elevator equipment
80%
Finishing works
90%
Internal engineering networks
90%
External engineering networks
100%
Improvement of the territory
100%
The house is completed
April
March
January
February
The house is completed
11 Photo
April
8 Photo
March
9 Photo
  • Work has been completed on installing internal utility networks.
  • Work has been completed on installing the plaster facade.
  • Work is underway to install windows and stained glass windows.
  • Work has been completed on installing a ventilated facade.
  • Finishing works are being carried out.
  • Work has been completed on installing external utility networks.
  • Improvement work is being carried out.
February
8 Photo
  • Work is underway to install internal utility networks.
  • Work is underway to install a plaster facade.
  • Work is underway to install windows and stained glass windows.
  • Work is underway to install a ventilated facade.
  • Finishing works are being carried out.
  • Work is underway to install external utility networks.
  • Improvement work is being carried out.
January
8 Photo
  • Work is underway to install internal utility networks.
  • Work is underway to install a plaster facade.
  • Work is underway to install windows and stained glass windows.
  • Work is underway to install a ventilated facade.
  • Finishing works are being carried out.
  • Work is underway to install external utility networks.
  • Improvement work is being carried out.